CONSTRUCTION PROJECT CONTROLS

Test the plan.
Connect the
project.

Planvium tests your construction schedule against build order, the contractor’s method and similar past work. Then it connects approved progress, drawings and delay evidence to one locked plan.

For infrastructure owners, PMCs and EPC teams.

CHECK→LOCK→TRACK→EXPLAIN→FORECAST

Working test system · Early beta · Pilot partners welcome

01 / ENTER THE ENGINE

CHECK FIRST. CONNECT EVERYTHING AFTER.

One tested plan.
The whole project.

The drawings, the schedule and site progress already exist. Planvium connects them before their combined effect reaches the monthly review.

↗ Choose a capability.
Or follow the story below.

Approved. Locked. Traceable.Progress · Drawings · Quantities and contract value · RFIs and issues · Delay evidence · 4D · Status finish · Project answersSee all eight connections ↗

01 / ASSURANCE

Works · Test system

Before you trust the plan, test it.

Check the task links, the construction order, the contractor’s method and durations from similar plans. A planner reviews the findings before the plan is accepted and locked.

A check without enough evidence is “not assessable”. Findings are questions for professional review, never automatic approval.

See the product evidence ↗
THE PLAN UNDER INSPECTIONILLUSTRATIVE EXAMPLES

A date is only as real as its dependencies.

REQUIRED DRAWINGAwaiting approvalNeeded before work starts
FOUNDATION STARTMondayThe plan appears ready

The schedule says “start”. The drawing says “wait”. The missing link makes the date unreliable.

The foundation starts Monday. The drawing is still waiting for approval. Without the link, the schedule hides the problem.

14 checks follow the DCMA approach. Findings support a planner’s judgement; they are not a certification.

PLANNER REVIEWSOWNER ACCEPTSPLAN LOCKED

02 / CONSTRUCTION LOGIC

Metro viaducts tested · Integration next

Build the sequence. Then the structure.

Follow each physical dependency, from foundation to girder. Then test an impossible order.

SCROLL TO ASSEMBLE ↓01 / 05
FOLLOW THE BUILD ORDERILLUSTRATION
VIADUCT / BUILD SEQUENCEStep 1 of 5

Scroll to assemble the span, or choose a step below.

Everything above starts with a supported foundation.

Illustrative sequence. Validated scope: metro and viaduct construction logic.

03 / EXECUTION CONTROL

Works · Test system

Submitted. Reviewed. Approved.

A field update passes through a human decision before it changes approved project progress.

  1. 01

    The field reports 99%.

    A new submission arrives. The last approved position remains at 91% while the evidence is reviewed.

  2. 02

    A person makes the decision.

    Review the update, then try “Approve the update”. Scrolling through this example never approves work for you.

  3. 03

    Progress changes. The baseline stays.

    An approved update advances the execution overlay. The original commitment remains available for comparison.

The committed baseline stays fixed. Approved progress drives the execution overlay.

See the product evidence ↗
THE APPROVAL GATESPAN 022 / DECK SLAB
SCROLL TO FOLLOW ↓01 / 03
FIELD SUBMISSION99%

Waiting for review

APPROVED TRUTH91%

Last approved position

IMPORTED BASELINEOriginal commitment preserved.
LOCKED

Illustrative review · A submission changes project truth only after approval.

04 / DELAY INTELLIGENCE

Works · Test system

Every revision leaves a trace.

See where the completion date moved, window by window. Keep the recorded movement and its explanation connected.

  1. 01

    First, a five-day movement.

    Window W1 records the initial shift in completion. Start with the revision comparison and its linked records.

  2. 02

    Then, eighteen more days.

    W2 adds 18 working days. The cumulative movement is now 23 days against the committed programme.

  3. 03

    Recovery changes the picture.

    W3 recovers five working days, leaving 18 overall. Movement is measurable; responsibility still needs review.

MetroLink M-01 demonstration. Movement is measured; causation and responsibility require review.

See the product evidence ↗
WHERE COMPLETION MOVEDRECORDED REVISIONS
SCROLL TO FOLLOW ↓01 / 03
CUMULATIVE FINISH MOVEMENT+5working days
W1selected window
+5movement
W1+5 cumulative
+18movement
W2+23 cumulative
−5recovered
W3+18 cumulative
31-May-2026 → 30-Jun-2026Reach 5 water-main diversion overran

Working days · Recorded demonstration windows · Movement measured against the committed programme.

05 / PLANVIUM AI

Early beta · Read only

An answer. With its evidence.

Planvium calculates. AI explains. People decide. The early assistant is strongest at explaining findings already calculated by Planvium.

  1. 01

    Begin with the project question.

    Why was Reach 6 piling held? The trail starts with RFI-0014 and the uncharted services it records.

  2. 02

    Connect instruction to activity.

    The site instruction suspends piling at the affected locations. The linked activity identifies Pier 49 in Reach 6.

  3. 03

    Read the explanation with its sources.

    Planvium AI connects the records into an explanation you can inspect. People retain the decision on causation and entitlement.

Early beta · Read only. AI never changes a plan, approves progress or decides delay claims. The linked-record example illustrates the direction; wider document retrieval is next.

See the product evidence ↗
AN ANSWER WITH A TRAILDIRECTION / ILLUSTRATION
SCROLL TO FOLLOW ↓01 / 03

Follow the query, the instruction and the affected activity. Scroll through the evidence or open the explanation above.

01 / QUERY
RFI-0014

Uncharted HT
and telecom services

Request for information
02 / INSTRUCTION
Suspend piling

At the affected
locations

SITE INSTRUCTION
ML-M01-SI-0032
03 / ACTIVITY
Pier 49

Reach 6
Piling work

M01-ZB-P049-PIL

Illustrated answer from seeded records · Wider document retrieval is next · People review causation and entitlement.

06 / PRODUCTIVITY PREDICTION

Roadmap · Interactive illustration

Change the rate. See the difference.

Explore how production rate changes the indicative duration of the remaining work.

  1. 01

    Start with completed work.

    In this hypothetical example, 40 of 100 deck segments are complete. Sixty still need to be installed.

  2. 02

    Turn quantity into a rate.

    Forty segments over ten working days gives a recent rate of four per day. Change the assumed rate to explore the effect.

  3. 03

    See what the remaining work implies.

    At four per day, sixty segments take fifteen working days. This explains one work package, not the project finish date.

Today: the status finish is recalculated from approved progress. Next: productivity-based prediction, once proven on real project history. The rate example is an illustration, not a project forecast.

THE WORK LEFT TO DODECK SEGMENT INSTALLATION
SCROLL TO FOLLOW ↓01 / 03

Hypothetical productivity illustration

40 completed60 remaining

40 segments ÷ 10 working days = 4/day recent rate

REMAINING QUANTITY ÷ ASSUMED RATE

60segments÷4/ day=

15working days
remaining

Assumes the same work and conditions, with no new interruptions. One work package; not a project completion date.

Where Planvium prediction is heading

Productivity P50/P80 forecasts and recovery comparison are on the roadmap. The aim: connect approved production rates to the remaining programme and compare recovery options.

P50/P80 describe completion dates with different confidence levels. This example does not calculate either.

Illustrative district connecting bridges, rail, buildings and a data centre

THE WORK CHANGES. THE NEED FOR CONTROL STAYS.

One connected view.
Across the built world.

AI-generated architectural concept

DIFFERENT PROJECTS. CONNECTED DECISIONS.

Beyond a single
kind of project.

Change the infrastructure. Explore what needs to happen before the next milestone.

Illustrative infrastructure
THE CONTROL QUESTION

From the first pile to the first passenger.

Connect a utility clearance, the piling front it holds and the opening milestone it may affect.

  1. 01Utility clearance
  2. 02Viaduct
  3. 03Track & systems
  4. 04Testing
  5. 05Passenger service

Illustrative applications · Not customer deployment claims

FROM A RECORD TO A DECISION

One late drawing.
One clear decision.

“Eight days late” is a record. How much of that can the project absorb? Connect the drawing to its work, and the answer becomes useful.

PILE CAP P17 / ILLUSTRATION

Late means after the work needs the drawing. The buffer (float) belongs to the whole chain and can be spent only once.

8days late3days of buffer5days of schedule risk
DrawingPile cap P17PierPier capGirder
ACTION TO REVIEWDesign Manager: review the approval date.

Completion could move by up to 5 days if this chain drives the project finish. Check the current critical path before acting.

Interactive illustration, not a live forecast. Drawing and submittal risk works in the test system; equivalent RFI risk is in development.

WHAT MAKES PLANVIUM DIFFERENT

The plan gets tested.
The evidence stays connected.

Schedule tools build the plan. Document systems hold the records. Planvium tests the plan against the work, then connects the records to the activities they affect.

01

Test against construction reality.

Build order, the contractor’s method, similar past plans and 14 schedule-quality checks. Every finding has evidence for a planner to review.

02

Keep one accepted baseline.

Lock the accepted plan. Link drawings, approved progress, quantities and delay records to the same work. The baseline remains available for comparison.

03

Make the effect understandable.

See what is held, what can absorb the delay and who needs to act. Planvium calculates. AI explains. People decide.

WHAT CONNECTS TO THE PLAN

Choose a connection to see what it means.

ONE TRUSTED PLANApproved · Locked · Traceable
Works · Test system

See the work a drawing can hold.

Link a required drawing or submittal to its activity. Compare the expected approval date with the date the work needs it and the available buffer.

Explore this connection
70real metro plans in the evidence libraryAbout 52 clearly separate plans · Planned durations, not actual productivity
8projects run through the product2 real plans for analysis · 6 sample projects for the full workflow
Early betaWorking in our test systemNo paying customers or live pilot yet · Product status as of 6 October 2026

“The drawings existed. The schedule existed. The progress existed. But the warning signs came together too late.”

Praveen Rana · FounderCivil engineer · Executive MBA, IIM KozhikodeAbout nine years across site, planning, project systems and the owner’s side
START WITH YOUR OWN PLAN

A health check first.
A 75-day pilot next.

Bring one contract section. Your planners judge the findings, false alarms and review time saved. Build confidence before expanding.

Discuss a plan health check

Evidence and product status from Planvium’s October 2026 investor deck. Order rules and benchmarks are calibrated for metro viaducts. Planvium reads P6 plan files today; connections to other systems do not imply live integrations. Plans enter the evidence library only with the owner’s written consent.

THE PRODUCT BEHIND THE STORY

Real project controls.
Visible evidence.

Explore the actual Planvium screens behind assurance, reviewed execution, AI explanation and measured delay.

PLANVIUM / DEMONSTRATION PROJECTOpen full size ↗
Planvium 4D for MetroLink M-01: the 11.4 km corridor compared against the committed schedule and approved progress, playhead at 16 August 2026. Legend: in sequence 26, not started 387, built 672.
Actual product capture · Sample data · Working test system

Assurance starts the conversation.
The project keeps it connected.

Planvium connects schedule checks with approved execution, project records and measured delay. Your planning tools remain part of the process.

YOUR PROGRAMME IS THE NEXT STEP

Test the plan.
Act before the delay.

Start with a plan health check on one contract section. Then scope a 75-day pilot with your planners, your questions and measurable results.

Discuss your project ↗

For infrastructure owners, PMCs and EPC teams.